My GoldSim water balance model includes a calibration portion using historical data and a predictive portion using forecasted data. Is it possible to shorten the run time of the model by running the calibration portion (4 years) deterministically and the predictive portion probabilistically?
For more background, the client is only interested in the predictive portion of the model. However, the calibration portion affects many parameters, and it would be a lot of work to manually reset these parameters to the values they are at the end of the calibration. If we could run the model deterministically for these years only, it would shorten the run time, reduce the chance of error in copying over values and save a lot of work.